San Francisco's fiscal year runs July 1 to June 30, but the budget is never written in the year it is spent. The mayor's budget book describes the annual cycle as starting in September and wrapping up in July, and the people who run it treat the calendar as gospel. Here is the whole cycle, month by month, using the dates from the 2026 round, which produced the two-year budget for fiscal years 2026-27 and 2027-28.
One note before the calendar. Since voters passed Proposition A on November 3, 2009, the city has budgeted two years at a time, with the second year revisited the year after. A majority of departments keep a rolling two-year budget, and four of them (the Airport, the Port, the Public Utilities Commission and the Municipal Transportation Agency) have had fixed two-year budgets since fiscal year 2010-11. The calendar below repeats every year, but the depth of the work varies: in even-numbered years the city also produces the Joint Report forecast, and in odd-numbered years a Five-Year Financial Plan.
September to November: the revenue forecast
It starts in September, with preliminary revenue projections for the coming budget years. The Controller is the city's chief financial officer and is responsible for projecting how much revenue is available. These early numbers tell the mayor's staff roughly how much room there is before a single department has asked for a dime.
In the meantime, the Controller's Office, the Mayor's Office and the Board of Supervisors' Budget and Legislative Analyst work on the long-range plan. In odd-numbered calendar years they publish a Five-Year Financial Plan, in December, and in even-numbered years a Joint Report that updates it. Voters first required the Joint Report in 1994, and since fiscal year 2011-12 it has looked four years ahead.
December: the instructions and the first forecast
In December the Mayor's Office and the Controller's Office send budget instructions to departments: the detailed guidance on how to prepare a request. In the 2025-26 cycle this was also the month of the first big number. On December 19, 2025 the Mayor's Office, the Controller and the Board's analyst released an update to the Five-Year Financial Plan projecting a General Fund deficit of $296.3 million in fiscal year 2026-27 and $640.3 million in 2027-28. Because the projected deficit went past $1 billion later in the forecast period, the mayor told departments to propose permanent spending reductions totaling $400 million. how the two-year budget closed a $642 million gap tells that story.
Between December and early February, departments put their requests together.
January and early February: the six-month report
The Controller publishes the Six-Month Budget Status Report in early February. It projects the year-end status of the General Fund and key special revenue and enterprise funds from activity between July and December. Problems it flags can feed into mid-year adjustments, and it is the first hard evidence of whether the current year is tracking the budget.
February 1 is also the day the Board's Budget and Appropriations Committee opens its annual season. The committee meets Wednesdays at 1:30 p.m. from February 1 to August 1. Its sibling, the Budget and Finance Committee, meets Wednesdays at 10:00 a.m. all year.
Mid-February: requests due
Departments hand their budget requests to the Controller by mid-February. The Controller consolidates and verifies them, then forwards the proposals to the Mayor's Office of Public Policy and Finance in early March. For a department head, mid-February is the deadline that counts. For a resident, February through May is the window to be heard: the mayor's staff run an outreach process during those months, meet with community groups and take budget priorities by email and an online form.
March: the Joint Report update
In even-numbered years, March brings the Joint Report. The 2026 edition was published on March 31 and updated the Five-Year Financial Plan for fiscal years 2026-27 through 2029-30. It showed a two-year shortfall of $642.8 million: $168.5 million in the first year and $474.3 million in the second.
From March through June, the mayor's budget staff dig into each request, weigh the policy and service implications and decide what to fund. The Controller certifies all revenue estimates, and before the budget is introduced the Controller confirms that it is balanced and accurate.
May 1: the enterprise budgets
Not every budget goes to the Board on the same day. The mayor introduces the proposed Enterprise department budgets to the Board by May 1. Enterprise departments such as the Port, the Municipal Transportation Agency, the Airport and the Public Utilities Commission earn their revenue from charges for service rather than from the General Fund, and together they make up 55 percent of the city's total budget. The Controller's Nine-Month Budget Status Report, published in early May, reports activity from July through March.
June 1: the General Fund budget
By the first business day in June, the mayor presents a balanced two-year proposal. The General Fund budget is introduced to the Board of Supervisors on June 1. In 2026 that meant the $16.9 billion proposal for fiscal year 2026-27 and $17.2 billion for 2027-28, and the book published that day (How to read the San Francisco budget book) is the document analysts and reporters live in for the rest of the summer.
June is also when the Budget and Appropriations Committee holds its public hearings on departmental requests. The committee works with the Board's Budget and Legislative Analyst, who reviews each department's proposal, compares it with prior-year spending and forwards a report recommending reductions. The committee weighs those recommended cuts, along with department and public input, before making final recommendations to the full Board. Because the budget must balance, any reduction to General Fund departments turns into unallocated money the Board can use for new services or to offset proposed cuts, often called addbacks. The Board draws up a list of budget policy priorities to guide the choices. The committee then votes to approve the amended budget and forwards it to the full Board by June 30. The Budget and Appropriations Committee covers that work in detail, including how public comment day works.
July 1: the new fiscal year starts, before the budget is final
The fiscal year begins on July 1, and the budget is not yet law. Because budget review spills over into the new fiscal year, the Board passes the Interim Budget, usually the mayor's proposal, as a continuing resolution. It serves as the operating budget until the final budget is adopted in late July.
July 15 to August 1: two votes
The charter requires the full Board to vote on the budget twice between July 15 and August 1. The first reading comes on the first Tuesday after July 15. At that reading any supervisor may propose amendments, and a simple majority adds them. The second reading is the final vote. If amendments are proposed at the second reading, the budget needs another reading a week later, and final passage must still come before the August 1 deadline. How an idea becomes an ordinance at the Board of Supervisors explains why ordinances need two readings.
August: the mayor's signature
After final passage the budget goes back to the mayor as the Budget and Appropriation Ordinance. The mayor has 10 days to approve it. The mayor can sign it, which makes it effective immediately, or veto any portion, which sends it back to the Board; the Board has 10 days to override any or all vetoes with a two-thirds vote. If the mayor does nothing within the 10 days, the budget becomes law without a signature. The mayor typically signs by August. In 2026 the Board passed the budget unanimously and the mayor signed it.
All year: execution and adjustments
Once the budget is law, spending is the departments' job. The Mayor's Office and the Controller monitor spending through the year, and the Board evaluates department performance measures from time to time. Departments can change the budget during the year in two ways: a supplemental appropriation request, when a department finds it lacks the resources to operate through year-end, or grant appropriation legislation, when an outside entity awards money. Both need Board approval before going to the mayor for signature.
Where residents can plug in
The calendar doubles as a map of the moments when a resident can be heard. Each has a different door.
- February to May. The Mayor's Office takes budget priorities by email and online form and meets community groups while it decides what to propose. This is the stage with the most flexibility, because nothing has been written down yet.
- June. The Budget and Appropriations Committee holds public hearings on departmental requests and solicits public input. Public comment day is the best-known chance to speak, and the Board's meeting page explains how to comment in person, by phone or in writing. See How to follow the Board of Supervisors from home.
- July. The two full-Board votes take comment like any other item. By then the committee has made its recommendations, so the most useful comments name a specific line and a specific amendment.
- All year. Supplemental appropriations and grant appropriations come to the Board through the ordinary legislative process, so a department's mid-year request for more money is a public item with a file number.
A reader who would rather follow the numbers than the meetings can use the Controller's status reports as checkpoints: the Six-Month report in early February and the Nine-Month report in early May show whether the current year is running ahead or behind, which is the best predictor of how much room the next budget has. See The Controller's reports and the City Survey.
A year at a glance
| When | What happens |
|---|---|
| September | Preliminary revenue projections |
| December | Budget instructions to departments; Five-Year Financial Plan or update |
| Early February | Controller's Six-Month Budget Status Report; Budget and Appropriations Committee season opens February 1 |
| Mid-February | Department requests due to the Controller |
| Early March | Controller forwards proposals to the Mayor's Office |
| March | Joint Report (even years) |
| May 1 | Enterprise department budgets introduced; Nine-Month report in early May |
| June 1 | Mayor introduces the General Fund budget |
| June | Budget and Appropriations hearings; committee forwards the budget by June 30 |
| July 1 | Fiscal year starts; Interim Budget in effect |
| July 15 to August 1 | Two Board votes |
| August | Mayor signs (10-day window) |
The easiest way to follow the cycle yourself is to bookmark the city's budget information page and the Board's committee schedule. City budget and finance describes who does what, and The Five-Year Financial Plan and the structural deficit explains the long-range forecast that frames each year's decisions.