How to get a building permit
How San Francisco building permits work: PermitSF, who reviews a project, the Permit Center at 49 South Van Ness, walk-in service and checking status.
Almost anything built in San Francisco, from a new roof deck to a restaurant kitchen, passes through a permit. The system looks complicated because several city departments each look at a different part of a project, and the first mistake most applicants make is going to the wrong one. This guide sorts out who does what, where to go, and how to follow a permit once it is filed. It stays general on fees and review times, which depend on the project and change, and points you to the pages where the current figures live.
Who is involved
Two departments do most of the work on a building project:
- San Francisco Planning decides whether a use or a design fits the zoning and planning rules. It sits at 49 South Van Ness Avenue, and its main number is 628.652.7600. A project that needs a conditional use, a variance or a design review is an entitlement matter that goes to Planning first, and in some cases to the Planning Commission.
- The Department of Building Inspection (DBI) reviews plans for structural, fire, electrical, plumbing and accessibility requirements, issues the building permit and inspects the work. Its address is also 49 South Van Ness Avenue, and its main number is 628-652-3200.
Other agencies join when a project touches their area: the Fire Department, the Department of Public Health, the Public Utilities Commission for water and sewer connections, and Public Works for sidewalks, street trees and work in the public right-of-way. The city's permitting pages group permits into building permits, business permits, entitlements and zoning, public spaces such as streets, sidewalks and street trees, and event permits.
PermitSF
In 2026 the city began rolling out improved digital permitting services under the name PermitSF, an initiative that aims to make permitting customer-centric, fast, predictable, transparent and unified. The partner agencies include the Permit Center, DBI, the Office of Small Business, the Fire Department, Planning and Public Works. The practical effect is that more of the filing and tracking happens online. The sf.gov permitting page links to the latest update on what has changed; read it before you start, since screens and steps are being revised.
The Permit Center
The Permit Center brings several agencies under one roof so that routine permits can be handled in a single visit.
- Address: 49 South Van Ness Avenue, 2nd floor, San Francisco, CA 94103. Enter on South Van Ness and follow the signs.
- Hours: Monday, 9 a.m. to 5 p.m.; Tuesday through Friday, 8 a.m. to 5 p.m.; closed on public holidays. Over-the-counter plan review and the print center queues close at 4:30 p.m., and payments are accepted until 5 p.m. The Center recommends arriving in the morning, because midday is busier, and queues may close early if capacity is reached. Wait times are managed through an electronic queue system.
- Staff: Representatives from the City Administrator, DBI, the Fire Department, the Department of Public Health, the Public Utilities Commission, Public Works, Planning, the Office of Small Business and the Office of Contract Administration.
- Services: Over-the-counter permits for construction, business and special events; printing, copying and scanning; and notary services, which you order, pay for and schedule online.
- Contact: 628-652-4900 or [email protected]. The Center asks callers to leave an email address with a voicemail and says it replies within two business days.
The Center is walk-in service for over-the-counter work. Larger or more complicated projects are submitted directly to DBI rather than handled at the counter.
Choosing the path
Think of a project in three tiers.
- Simple, routine work. The Permit Center issues some construction, business and special event permits over the counter. Its staff can tell you whether your project qualifies.
- A standard project that needs plan review. A kitchen remodel that moves walls or plumbing, or an addition, goes through plan review. Planning and DBI may both look at it. Expect questions and requests for corrections.
- A project that needs a discretionary approval. A change of use, a variance or a new building has to clear Planning's entitlement process, including public notice, before building permits can be issued. The Planning Commission and the Board of Appeals are the public bodies that hear these matters. The Board of Appeals hears appeals of many permits, determinations and decisions.
If you are unsure which tier applies, call the Permit Center or look up the address on the Planning Department's Property Information Map, which displays zoning, the building's history and existing permits.
Fees
Fees depend on the type and cost of the work and are set in published schedules by each department. This guide does not quote amounts because they change and vary by project; the DBI and Planning fee schedules on their websites list them, and a permit technician at the Permit Center can give an estimate for your project. Ask for the total, including each agency's share, before you file.
Checking status
The city's permitting page lists three tools for following a permit: the Property Information Map, the building permit tracking system and the Public Works permit search. Enter the address or the application number to see where the file is, what has been approved and what is waiting. When a review asks for a correction, respond promptly; a permit that sits waiting for the applicant is the commonest source of delay.
Practical advice
- Start at the address. Look up the property, its zoning and past permits before you draw plans.
- Hire for the job. A licensed contractor or an architect familiar with San Francisco requirements knows what Planning and DBI expect.
- Plan for inspections. A permit is not the end. DBI inspects work at stages, and the final inspection closes the permit.
- Do not build first. Work without a permit can bring a stop-work order and fines, and it complicates a later sale.
- Mind the street. If your project uses the sidewalk, a street space or a tree, the Public Works permit is a separate piece of paper; see San Francisco Public Works.
- Report problems you see. Construction without a posted permit, or hazards, can be reported through 311; Using 311 in San Francisco, by phone, app or web explains how.
If your project is a business in a commercial space, the permit process runs alongside business registration; Starting a business in San Francisco covers the order. For the departments themselves, see Department of Building Inspection and the Permit Center and San Francisco Planning.